A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits. The implementation team has a strong interest in cost and schedule, and a limited interest in the benefits being produced. The client is only focused on benefits. Which of the following actions should the…
Nội dung câu hỏi
A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits. The implementation team has a strong interest in cost and schedule, and a limited interest in the benefits being produced. The client is only focused on benefits. Which of the following actions should the program manager take?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Focus on the internal stakeholders to ensure cost and schedule objectives are achieved.
- B. Balance stakeholder needs through the use of trade-offs among the stakeholder groups. — đáp án hiện tại
- C. Focus on the external stakeholders to ensure the intended benefits are achieved.
- D. Conduct a stakeholder meeting to allow everyone to state their priorities.