Câu 177: PgMP: Program Management Professional
A software deployment program for a multinational organization requires the engagement of subcontractors. During the program planning phase, the contracts manager informs the program manager that the primary subcontractor's agreement includes incentives that would potentially conflict with program objectives. What sho…
Nội dung câu hỏi
A software deployment program for a multinational organization requires the engagement of subcontractors. During the program planning phase, the contracts manager informs the program manager that the primary subcontractor's agreement includes incentives that would potentially conflict with program objectives. What should the program manager do first?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Review the contracts, and create a program budget contingency.
- B. Draft a change request for approval by the program steering committee.
- C. Ask the program management office (PMO) to conduct a risk assessment.
- D. Review the program charter, and update program objectives accordingly. — đáp án hiện tại