Câu 15: PgMP: Program Management Professional
The program manager has a global program with five component projects. The program sponsor wants the management plans, processes/procedures, and technology to be uniform across the program. The requirements will create issues and result in increased costs The program sponsor is new and has imposed these new requiremen…
Nội dung câu hỏi
The program manager has a global program with five component projects. The program sponsor wants the management plans, processes/procedures, and technology to be uniform across the program. The requirements will create issues and result in increased costs The program sponsor is new and has imposed these new requirements six months into a three-year program. What should the program manager do next?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Accept what the program sponsor requires and implement the changes.
- B. Discuss the proposed changes with the stakeholders and project managers, and give the program sponsor the best option. — đáp án hiện tại
- C. Respond to the program sponsor if the program sponsor asks about it a second time. — đáp án hiện tại
- D. Present the risks and benefits of the changes to the program sponsor.