CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 103: PgMP: Program Management Professional

You are the program manager for your organization. Your current program has a budget at completion of $3,450,000 and is expected to last two years. The program is currently 30 percent complete and has spent ten percent more than what it should have to arrive at this point in the program schedule. Based on this informa…

Nội dung câu hỏi

You are the program manager for your organization. Your current program has a budget at completion of $3,450,000 and is expected to last two years. The program is currently 30 percent complete and has spent ten percent more than what it should have to arrive at this point in the program schedule. Based on this information, what is estimate at completion (EAC) for this program?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. $2,656,500
  2. B. There is not enough information to know.
  3. C. $3,795,000 — đáp án hiện tại
  4. D. $1,035,000

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề