Câu 82: PgMP: Program Management Professional
A program is midway through the program delivery phase when a key stakeholder asks if the program is meeting its defined objectives. How should the program manager demonstrate the program's progress?
Nội dung câu hỏi
A program is midway through the program delivery phase when a key stakeholder asks if the program is meeting its defined objectives. How should the program manager demonstrate the program's progress?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Define the key performance indicators (KPIs) for the program's outcome.
- B. Invite the key stakeholder to review the program charter and the program objectives.
- C. Provide additional program performance reports to the key stakeholder. — đáp án hiện tại
- D. Maintain the benefits register and provide it to the key stakeholder.