Câu 207: PgMP: Program Management Professional

A two-year program is coming to an end. Many of the initial governance board members have moved from their current posts or left the company. Several new members have joined, but have a short association with the program, which changes the board's expectations and focus. During the final phase gate review, some board…

Nội dung câu hỏi

A two-year program is coming to an end. Many of the initial governance board members have moved from their current posts or left the company. Several new members have joined, but have a short association with the program, which changes the board's expectations and focus. During the final phase gate review, some board members are uncertain of their roles and expectations in the process. How should the program manager handle this situation?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Review the final program outcome with the program sponsor
  2. B. Prepare a program change request utilizing new board member input
  3. C. Review the strategic plan and benefits management plan with the board — đáp án hiện tại
  4. D. Present the final program status, costs, and schedule reports