Câu 146: PgMP: Program Management Professional
A program manager has four projects pending approval. Senior management asks the program manager to identify a project for potential elimination based on the return on investment. The program manager has the following information to guide and support the decision: Which project should the program manager select to be…
Nội dung câu hỏi
A program manager has four projects pending approval. Senior management asks the program manager to identify a project for potential elimination based on the return on investment. The program manager has the following information to guide and support the decision: Which project should the program manager select to be cancelled?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Project A
- B. Project B
- C. Project C
- D. Project D — đáp án hiện tại