Câu 34: PgMP: Program Management Professional

The program sponsor requests a weekly performance report. The tools and techniques to monitor and control program performance include which of the following?

Nội dung câu hỏi

The program sponsor requests a weekly performance report. The tools and techniques to monitor and control program performance include which of the following?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Program management performance variances, business criteria reweighting, root cause identification, and statistical sampling.
  2. B. Interviewing, SWOT analysis, run chart, and matrix-based charts.
  3. C. Earned value management, financial reporting systems, performance measurement techniques, and program management information systems. — đáp án hiện tại
  4. D. Delphi technique, scatter diagram, Pareto chart, and organization charts.