Câu 98: PMI Agile Certified Practitioner

During a retrospective, team members suggest process improvement ideas. The agile team lead knows that, while many of these ideas are different from standard practices, a few of them are good. What should the agile team lead do?

Nội dung câu hỏi

During a retrospective, team members suggest process improvement ideas. The agile team lead knows that, while many of these ideas are different from standard practices, a few of them are good. What should the agile team lead do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Require the team to try only those ideas that will ensure success
  2. B. Allow the team to try ideas, but remind them that results will be reviewed by high-ranking executives
  3. C. Associate idea successes and failures with the team's incentive plan to ensure accountability
  4. D. Encourage the team to try the ideas, even if failure may be the outcome — đáp án hiện tại