During a planning session, four out of five team members vote to include eight story points in a particular story, while the fifth member votes for five story points. How should this be handled?
Nội dung câu hỏi
During a planning session, four out of five team members vote to include eight story points in a particular story, while the fifth member votes for five story points. How should this be handled?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. The story should be assigned eight story points as per the majority vote
- B. The story should be added to the backlog and reassessed later
- C. The story should be assigned points after a discussion with the fifth team member to see if a consensus can be reached — đáp án hiện tại
- D. The decision for the number of story points should be made by the customer