A scrum team has conducted regular retrospectives to discuss immediate concerns and the implementation of improvement actions. Despite this, after a few iterations, the same concerns resurface. What should the team have done to improve retrospective outcomes?

Nội dung câu hỏi

A scrum team has conducted regular retrospectives to discuss immediate concerns and the implementation of improvement actions. Despite this, after a few iterations, the same concerns resurface. What should the team have done to improve retrospective outcomes?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Invited subject matter experts (SMEs)
  2. B. Conducted problem detections to determine root causes — đáp án hiện tại
  3. C. Measured and reported the outcome of improvement actions to the team
  4. D. Kept track of all current issues in a log, and then reviewed their progress at the end of every iteration