Câu 96: PMI Agile Certified Practitioner
An agile team and a traditional development team are working together on a project. Each team exceeds expectations regarding deliverables; however, issues arise when the deliverables are integrated. What should the agile practitioner do?
Nội dung câu hỏi
An agile team and a traditional development team are working together on a project. Each team exceeds expectations regarding deliverables; however, issues arise when the deliverables are integrated. What should the agile practitioner do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Foster stronger communication by hosting cross-organizational meetings between the two teams — đáp án hiện tại
- B. Suggest merging the teams to avoid misunderstandings
- C. Create stories from full technical specifications to avoid ambiguity
- D. Co-locate the teams to encourage osmotic communication