An agile team and a traditional development team are working together on a project. Each team exceeds expectations regarding deliverables; however, issues arise when the deliverables are integrated. What should the agile practitioner do?

Nội dung câu hỏi

An agile team and a traditional development team are working together on a project. Each team exceeds expectations regarding deliverables; however, issues arise when the deliverables are integrated. What should the agile practitioner do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Foster stronger communication by hosting cross-organizational meetings between the two teams — đáp án hiện tại
  2. B. Suggest merging the teams to avoid misunderstandings
  3. C. Create stories from full technical specifications to avoid ambiguity
  4. D. Co-locate the teams to encourage osmotic communication