Câu 83: PMI Agile Certified Practitioner
A product owner complains that some of the requirements identified several iterations ago have not been implemented. The product owner wants to know why the status of these requirements was not communicated. What should the Scrum Master do?
Nội dung câu hỏi
A product owner complains that some of the requirements identified several iterations ago have not been implemented. The product owner wants to know why the status of these requirements was not communicated. What should the Scrum Master do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Point out that the team chose to work on other requirements to speed up the project
- B. Ensure that the product owner reviews the contents of the information radiator — đáp án hiện tại
- C. Ensure that the next sprint planning meeting reviews the satisfaction histogram
- D. Point out that it is the responsibility of the product owner to clarify requirements