Câu 68: PMI Agile Certified Practitioner

At the end of a product development phase, an agile project team confirms that all tests have passed. The product is released, but the customer complains that it is deficient. What should the project team have done prior to product release?

Nội dung câu hỏi

At the end of a product development phase, an agile project team confirms that all tests have passed. The product is released, but the customer complains that it is deficient. What should the project team have done prior to product release?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Requested approval from the project sponsor
  2. B. Undertaken a review of all requirements
  3. C. Conducted an end-of-phase demonstration — đáp án hiện tại
  4. D. Performed a retrospective to validate project deliverables