Two similar stories, A and B, are estimated at 3 story points. Story C, estimated at 8 points. After an iteration in which A and C were completed, it is found that story A took much longer than story C. What should the agile practitioner do?

Nội dung câu hỏi

Two similar stories, A and B, are estimated at 3 story points. Story C, estimated at 8 points. After an iteration in which A and C were completed, it is found that story A took much longer than story C. What should the agile practitioner do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Assign story B more than 8 story points so to provide a better estimate
  2. B. Add points to story B's iteration to account for the error but keep story B at 3 points
  3. C. Assign more resources to story B to bring it in line with the estimate
  4. D. Re-estimate all stories including values for A, B and C — đáp án hiện tại