Two similar stories, A and B, are estimated at 3 story points. Story C, estimated at 8 points. After an iteration in which A and C were completed, it is found that story A took much longer than story C. What should the agile practitioner do?
Nội dung câu hỏi
Two similar stories, A and B, are estimated at 3 story points. Story C, estimated at 8 points. After an iteration in which A and C were completed, it is found that story A took much longer than story C. What should the agile practitioner do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Assign story B more than 8 story points so to provide a better estimate
- B. Add points to story B's iteration to account for the error but keep story B at 3 points
- C. Assign more resources to story B to bring it in line with the estimate
- D. Re-estimate all stories including values for A, B and C — đáp án hiện tại