Câu 140: PMI Agile Certified Practitioner
Two teams have received project requirements and completed estimates. Team A estimates 420 story points for scope and 30 story points for velocity per sprint. Team B estimates 280 story points for scope and 20 story points for velocity per sprint. Both teams have same number of team members and have assumed a sprint d…
Nội dung câu hỏi
Two teams have received project requirements and completed estimates. Team A estimates 420 story points for scope and 30 story points for velocity per sprint. Team B estimates 280 story points for scope and 20 story points for velocity per sprint. Both teams have same number of team members and have assumed a sprint duration of 2 weeks. What can an agile practitioner conclude about team A and team B's estimate?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Team B has underestimated scope compared to team A
- B. Team A is more confident in delivering velocity than team B
- C. Both teams need to indicate their proposed technology before the estimates can be analyzed
- D. Both teams have estimated the project to be of same size — đáp án hiện tại
Cộng đồng