Câu 126: PMI Agile Certified Practitioner
Midway through a project, the product owner learns from the sponsor that a major component, which is already 20 percent complete, is unimportant to users. The component was part of the approved scope and a key selling point for the project. What should the product owner do next?
Nội dung câu hỏi
Midway through a project, the product owner learns from the sponsor that a major component, which is already 20 percent complete, is unimportant to users. The component was part of the approved scope and a key selling point for the project. What should the product owner do next?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Obtain approval from the change control board to discontinue the component
- B. Ask the team to continue developing the component
- C. Ask the team to discontinue developing the component — đáp án hiện tại
- D. Request the sponsor's formal approval to discontinue the component