CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 126: PMI Agile Certified Practitioner

Midway through a project, the product owner learns from the sponsor that a major component, which is already 20 percent complete, is unimportant to users. The component was part of the approved scope and a key selling point for the project. What should the product owner do next?

Nội dung câu hỏi

Midway through a project, the product owner learns from the sponsor that a major component, which is already 20 percent complete, is unimportant to users. The component was part of the approved scope and a key selling point for the project. What should the product owner do next?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Obtain approval from the change control board to discontinue the component
  2. B. Ask the team to continue developing the component
  3. C. Ask the team to discontinue developing the component — đáp án hiện tại
  4. D. Request the sponsor's formal approval to discontinue the component

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề