During an iteration review, the agile team asserts that a product is complete because development and review were finished. The product owner disagrees, since the product has not been tested. What should the agile practitioner do?
Nội dung câu hỏi
During an iteration review, the agile team asserts that a product is complete because development and review were finished. The product owner disagrees, since the product has not been tested. What should the agile practitioner do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Work with the agile team and product owner to agree on the definition of done — đáp án hiện tại
- B. Ask the sponsor to determine whether the product is completed
- C. Plan another review after the product has been tested
- D. Add testing to the backlog, and have the product owner reprioritize