CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 29: PMI Agile Certified Practitioner

A team using Kanban identifies that their cycle time has significant variation. After brainstorming, the team determines that the root cause is the stories' varying sizes and risks. What should the team do?

Nội dung câu hỏi

A team using Kanban identifies that their cycle time has significant variation. After brainstorming, the team determines that the root cause is the stories' varying sizes and risks. What should the team do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Reduce work in progress (WIP) limits to accommodate slack for riskier stories
  2. B. Create a triage step on the Kanban board to pre-identify risky stories
  3. C. Set a policy to break down stories larger than a specified complexity, then adjust the WIP — đáp án hiện tại
  4. D. Create a dedicated overflow swim lane on the Kanban board for stories that are too large

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề