Câu 146: PMI Agile Certified Practitioner
A team member has spent 5 days on a spike and the first set of experiments has not been successful. The issue is the development team member has determined a short-term rather than a long-term solution. What should the project leader do?
Nội dung câu hỏi
A team member has spent 5 days on a spike and the first set of experiments has not been successful. The issue is the development team member has determined a short-term rather than a long-term solution. What should the project leader do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Assign the spike to another resource to continue research for the long-term solution
- B. Re-estimate the spike, encourage experimentation and collaborate with the team — đáp án hiện tại
- C. Stop experimentation and negotiate the short-term solution with the customer
- D. Schedule a root-cause analysis with the development team on the main issues with the spike