Câu 113: PMI Agile Certified Practitioner

An agile coach realizes that a team responsible for a major release is a few months behind schedule. The marketing department is unaware of this delay, and is planning to start the marketing campaign and announce the release. What should the agile coach do?

Nội dung câu hỏi

An agile coach realizes that a team responsible for a major release is a few months behind schedule. The marketing department is unaware of this delay, and is planning to start the marketing campaign and announce the release. What should the agile coach do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Meet with the agile team lead to discuss ways to improve the team velocity and get back on track
  2. B. Use this as a learning opportunity and allow the team to handle the situation when the marketing campaign begins
  3. C. In the upcoming retrospective, discuss ways to improve sharing project status information
  4. D. Meet with the marketing stakeholders to explain that the team will miss the planned release date — đáp án hiện tại