Câu 81: PMI Agile Certified Practitioner
Senior management is frustrated at the lack of a detailed implementation plan that shows exactly when the project will end and when all requirements will be met. The team has been using a rolling wave planning approach so far on the project. How should the agile practitioner explain to senior management the benefits o…
Nội dung câu hỏi
Senior management is frustrated at the lack of a detailed implementation plan that shows exactly when the project will end and when all requirements will be met. The team has been using a rolling wave planning approach so far on the project. How should the agile practitioner explain to senior management the benefits of this approach?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. It ensures a consistent level of detail is available in the project schedule
- B. It prevents a wasteful build-up of requirements inventory that may never be processes — đáp án hiện tại
- C. It provides a concrete definition of product scope, cost and duration
- D. It allows the team to lock down the stories to be included in a release
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.