Câu 7: PMI Agile Certified Practitioner

Midway through a sprint, a team member discovers that the product design fails to adhere to the organization's enterprise architecture standards. Since this required escalation to the architecture team for further analysis and resolution, the team was unable to deliver its sprint goal and the sprint was cancelled. Wha…

Nội dung câu hỏi

Midway through a sprint, a team member discovers that the product design fails to adhere to the organization's enterprise architecture standards. Since this required escalation to the architecture team for further analysis and resolution, the team was unable to deliver its sprint goal and the sprint was cancelled. What should the team have done to avoid this?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Escalated the issue to management
  2. B. Ensured the early engagement of key stakeholders — đáp án hiện tại
  3. C. Provided feedback to the architecture team to change the enterprise architecture standards
  4. D. Raised an exception for non-adherence to the enterprise architecture standards for this product