Câu 54: PMI Agile Certified Practitioner

An agile team is planning the next iteration for a product release that has accumulated technical debt. What should the team do?

Nội dung câu hỏi

An agile team is planning the next iteration for a product release that has accumulated technical debt. What should the team do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Add code cleanup activities to the product backlog and request prioritization by the product owner — đáp án hiện tại
  2. B. Add code cleanup activities to the next iteration and request clarification from the product owner
  3. C. Add code cleanup activities to the next iteration and ask the product owner to end the current iteration
  4. D. Add code cleanup activities to the next release backlog and request documentation from the product owner