Câu 65: PMI Agile Certified Practitioner

After seeing the planned features for an upcoming release, a customer notes that a vitally important and complex one is missing. The team estimates that this feature significantly exceeds its average velocity. How can this issue be resolved?

Nội dung câu hỏi

After seeing the planned features for an upcoming release, a customer notes that a vitally important and complex one is missing. The team estimates that this feature significantly exceeds its average velocity. How can this issue be resolved?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Break down the feature into smaller parts, and commit to complementing the minimum value product — đáp án hiện tại
  2. B. Complete the iteration to which they have already committed, and include the feature in the next release
  3. C. Change the planned features to include only the vitally important one
  4. D. Extend the iteration to complete the feature