Câu 16: PMI Agile Certified Practitioner

A legal department representative contacts the scrum master because, while the project's budget has been maintained, it has exceeded its original contracted time and scope. What should the scrum master do?

Nội dung câu hỏi

A legal department representative contacts the scrum master because, while the project's budget has been maintained, it has exceeded its original contracted time and scope. What should the scrum master do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Meet with the team to gain alignment with the legal department's need to stay within the contracted time and scope
  2. B. Work with the customer to narrow the scope
  3. C. Share the project's trajectory with the legal department — đáp án hiện tại
  4. D. Meet with the legal department to help them understand that the customer and the team are satisfied with the time and deliveries