Câu 57: PMI Agile Certified Practitioner
A development team for a small company experiences long delays between product completion and release for validation and testing. The company is concerned that this will impact its ability to complete in the market place. What analysis should the team use to understand the issues?
Nội dung câu hỏi
A development team for a small company experiences long delays between product completion and release for validation and testing. The company is concerned that this will impact its ability to complete in the market place. What analysis should the team use to understand the issues?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Risk management
- B. Variance and trend
- C. Kano model
- D. Fishbone-diagram — đáp án hiện tại
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.