Câu 70: PMI Agile Certified Practitioner

During a backlog refinement meeting, a senior team member raises a concern about an epic sizing that requires the use of a new interface for a vendor product. The product owner acknowledges this as a risk. What should the product owner do now?

Nội dung câu hỏi

During a backlog refinement meeting, a senior team member raises a concern about an epic sizing that requires the use of a new interface for a vendor product. The product owner acknowledges this as a risk. What should the product owner do now?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Log the risk in the risk register, and share the information with impacted stakeholders at the next monthly review meeting
  2. B. Create a spike story to determine what needs to be done to use the new interface — đáp án hiện tại
  3. C. Lower the epic's priority so that it can be deferred, and analyze it during backlog refinement meetings
  4. D. Move the work to the vendor, since they have better knowledge of interface implementation