During a backlog refinement meeting, a senior team member raises a concern about an epic sizing that requires the use of a new interface for a vendor product. The product owner acknowledges this as a risk. What should the product owner do now?
Nội dung câu hỏi
During a backlog refinement meeting, a senior team member raises a concern about an epic sizing that requires the use of a new interface for a vendor product. The product owner acknowledges this as a risk. What should the product owner do now?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Log the risk in the risk register, and share the information with impacted stakeholders at the next monthly review meeting
- B. Create a spike story to determine what needs to be done to use the new interface — đáp án hiện tại
- C. Lower the epic's priority so that it can be deferred, and analyze it during backlog refinement meetings
- D. Move the work to the vendor, since they have better knowledge of interface implementation