Câu 88: PMI Agile Certified Practitioner
A project is starting and the type of work is complex and suitable for agile. In assessing the team members, it appears that co-location would be a challenge. What should the agile practitioner do?
Nội dung câu hỏi
A project is starting and the type of work is complex and suitable for agile. In assessing the team members, it appears that co-location would be a challenge. What should the agile practitioner do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Select and implement collaboration tools to augment team interactions — đáp án hiện tại
- B. Provide each geographical area with their own product owner and divide the work between the teams
- C. Increase the number of requirements documents and ensure they are clearly communicated
- D. After several sprints, calculate velocity based on primary team location and use secondary team as reserve