During the implementation phase of a construction project to build a public hospital, the government issues a 1-week stop-work order for the whole project because some of the reports received from the project coordinator were lacking critical information and the associated risks could not be identified. What should th…

Nội dung câu hỏi

During the implementation phase of a construction project to build a public hospital, the government issues a 1-week stop-work order for the whole project because some of the reports received from the project coordinator were lacking critical information and the associated risks could not be identified. What should the construction professional have done to prevent this from happening?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Instructed the whole team to provide input for each report to increase their accuracy and precision
  2. B. Asked the project coordinator to provide a report tailored to the needs of each stakeholder group — đáp án hiện tại
  3. C. Issued a letter to the government inspectors beforehand to make sure all approvals were issued
  4. D. Requested the project sponsor for additional funding to pay for a more experienced project coordinator