A construction professional is working on a large complex project to build a first of its kind technology. The project is progressing toward detailed design and is required to go through a phase gate that must include a detailed risk register. The construction professional has identified a number of risks that may req…

Nội dung câu hỏi

A construction professional is working on a large complex project to build a first of its kind technology. The project is progressing toward detailed design and is required to go through a phase gate that must include a detailed risk register. The construction professional has identified a number of risks that may require contingency. What should the construction professional do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Use the Delphi technique to estimate the future demand for the project.
  2. B. Quantify the likelihood and probability of the cost and schedule impacts of the risks that require contingency. — đáp án hiện tại
  3. C. Host a facilitated workshop with subject matter experts (SMEs) to generate a list of potential risks and document them in a risk register.
  4. D. Run a Monte Carlo simulation to establish the contingency for the next phase of the project.