Câu 33: PMI Construction Professional
A construction professional is working on a large complex project to build a first of its kind technology. The project is progressing toward detailed design and is required to go through a phase gate that must include a detailed risk register. The construction professional has identified a number of risks that may req…
Nội dung câu hỏi
A construction professional is working on a large complex project to build a first of its kind technology. The project is progressing toward detailed design and is required to go through a phase gate that must include a detailed risk register. The construction professional has identified a number of risks that may require contingency. What should the construction professional do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Use the Delphi technique to estimate the future demand for the project.
- B. Quantify the likelihood and probability of the cost and schedule impacts of the risks that require contingency. — đáp án hiện tại
- C. Host a facilitated workshop with subject matter experts (SMEs) to generate a list of potential risks and document them in a risk register.
- D. Run a Monte Carlo simulation to establish the contingency for the next phase of the project.