Câu 22: PMI Construction Professional

The physical work is complete on an airport terminal expansion project and testing and commissioning have started. The contractor submits the completion certificate request. What should the construction professional do?

Nội dung câu hỏi

The physical work is complete on an airport terminal expansion project and testing and commissioning have started. The contractor submits the completion certificate request. What should the construction professional do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Approve the request as the physical work is complete and only testing and commissioning remain.
  2. B. Ask the operations department if they agree to take over without testing and commissioning being completed.
  3. C. Send the contractor a letter to complete testing and commissioning in parallel with processing the request.
  4. D. Reject the request because the testing and commissioning steps have not been completed. — đáp án hiện tại