Câu 24: PMI Construction Professional
A construction professional is assigned to a critical building project for a high-profile client with many stakeholders and communications channels. The client requests that the construction management firm start construction as soon as possible. During the planning phase, the project team is about to start using the…
Nội dung câu hỏi
A construction professional is assigned to a critical building project for a high-profile client with many stakeholders and communications channels. The client requests that the construction management firm start construction as soon as possible. During the planning phase, the project team is about to start using the Compass tool when the project sponsor suggests doing this later to expedite planning and commence with the construction as soon as possible. What should the construction professional do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Disagree with the project sponsor and ask the team to move forward with setting up the Compass tool as originally planned.
- B. Explain to the project sponsor that the Compass tool should be used as soon as the team is assembled to establish baseline assessments. — đáp án hiện tại
- C. Agree with the project sponsor and ask the team to postpone using the Compass tool until after the construction starts.
- D. Negotiate with the project sponsor to start the setup process for the Compass tool during planning and complete the initial setup during construction.