A design company decided to add building information modeling (BIM) to their services and took on a BIM pilot project with a client. The desired goals were the acquisition and retention of technical BIM skills and enhancing the company's ability to compete in this market. Upon completion, the project ended up with an…
Nội dung câu hỏi
A design company decided to add building information modeling (BIM) to their services and took on a BIM pilot project with a client. The desired goals were the acquisition and retention of technical BIM skills and enhancing the company's ability to compete in this market. Upon completion, the project ended up with an 80% cost overrun and a 100% schedule overrun. The main reasons for this include repetitive reviews of the design due to unexpected values contained within the software and additional resource hours to complete the work. Aside from these reasons, the client was happy with the quality, and the company will be considered for future projects. How should the construction professional summarize what the company achieved with this project?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. The additional money was well invested, because the client was satisfied and the quality was acceptable.
- B. The project took longer than planned, but the results were delivered and the client was satisfied.
- C. The unexpected values in the software will not be an ongoing issue, so the quality will improve.
- D. The company was most likely able to acquire the desired skills and is set up for the future. — đáp án hiện tại