During user acceptance testing, a defect is logged by a user from a department that did not participate in the requirements analysis. To avoid this situation and minimize impact on the project, the user should have been:
Nội dung câu hỏi
During user acceptance testing, a defect is logged by a user from a department that did not participate in the requirements analysis. To avoid this situation and minimize impact on the project, the user should have been:
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. interviewed to understand how the user’s work would be impacted.
- B. involved in the development and sign-off of the business requirements.
- C. given the opportunity to review the user acceptance test scripts.
- D. identified as a stakeholder as part of the stakeholder analysis. — đáp án hiện tại