Câu 15: PMI Professional in Business Analysis

A company’s management team has decided to deploy a new product. However, there is concern that users may not accept a new product that forces them to change existing practices. The business analyst should:

Nội dung câu hỏi

A company’s management team has decided to deploy a new product. However, there is concern that users may not accept a new product that forces them to change existing practices. The business analyst should:

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. adhere to the project plan to achieve project objectives.
  2. B. clearly communicate project objectives and attempt to defuse tensions. — đáp án hiện tại
  3. C. delay the application’s deployment until the conflicts have been resolved.
  4. D. voice user concerns to management and recommend that the project be closed.