Câu 44: PMI Project Management Office Certified Professional

An IT company hired a PMO Professional to lead the company's PMO. The PMO has been established for three years without showing real value to the organization. Which step should the PMO Professional prioritize to change this situation?

Nội dung câu hỏi

An IT company hired a PMO Professional to lead the company's PMO. The PMO has been established for three years without showing real value to the organization. Which step should the PMO Professional prioritize to change this situation?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Establish a new system for the PMO to automate its processes
  2. B. Develop new functions and services for the PMO
  3. C. Gather the PMO stakeholders' expectations and needs — đáp án hiện tại
  4. D. Develop a new PMO charter