Câu 27: PMI Project Management Office Certified Professional

A company decided to expand its PMO services to include strategic alignment and to participate in strategic planning. The company tasked a PMO professional with developing a framework to ensure the new services are properly planned, implemented, and governed. Which action should the PMO professional take to develop th…

Nội dung câu hỏi

A company decided to expand its PMO services to include strategic alignment and to participate in strategic planning. The company tasked a PMO professional with developing a framework to ensure the new services are properly planned, implemented, and governed. Which action should the PMO professional take to develop the requested framework?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Check compliance requirements for strategic planning.
  2. B. Conduct regular project audits and reviews.
  3. C. Implement strategic project portfolio management.
  4. D. Understand the stakeholders' expectations clearly. — đáp án hiện tại