Câu 40: PMI Project Management Office Certified Professional
A company aims to build a series of nuclear power plants and wants to establish a PMO to support its large-scale and high-risk strategy. The PMO professional has already developed the PMO vision, mission, and high-level strategy. What should the PMO professional do next?
Nội dung câu hỏi
A company aims to build a series of nuclear power plants and wants to establish a PMO to support its large-scale and high-risk strategy. The PMO professional has already developed the PMO vision, mission, and high-level strategy. What should the PMO professional do next?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Determine the most common risks and pain points in the energy sector.
- B. Outline the expected benefits of the program's strategy.
- C. Identify critical factors that shape PMOs across the energy industry.
- D. Define the PMO scope, authority, roles, and responsibilities. — đáp án hiện tại