Câu 118: PMI Risk Management Professional

After years of experience, a project manager becomes the lead manager for a company. This new lead manager asks all project managers to use a specific technique when they perform qualitative risk analysis on their projects. This technique consists of achieving the relative weighting of the project's objectives in term…

Nội dung câu hỏi

After years of experience, a project manager becomes the lead manager for a company. This new lead manager asks all project managers to use a specific technique when they perform qualitative risk analysis on their projects. This technique consists of achieving the relative weighting of the project's objectives in terms of priority to the stakeholders. What is the name of this technique?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Relative Weighting of the objectives of Stakeholders (RWS)
  2. B. Objectives Stakeholders Weighting (OSW)
  3. C. Quantitative Weighted Analysis (QWA) — đáp án hiện tại
  4. D. Analytic Hierarchy Process (AHP)