Câu 60: PMI Risk Management Professional

A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue. What should the risk manager do next to find out the corr…

Nội dung câu hỏi

A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue. What should the risk manager do next to find out the correct limit?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Use industry standard risk thresholds
  2. B. Find out the stakeholders’ risk appetite
  3. C. Review the agreed-upon risk tolerance — đáp án hiện tại
  4. D. Perform a sensitivity analysis of the risk