Câu 81: PMI Risk Management Professional
A risk is identified early in the project. After six months, it is determined that the risk does not apply to this particular project. How should the risk be handled by the risk manager?
Nội dung câu hỏi
A risk is identified early in the project. After six months, it is determined that the risk does not apply to this particular project. How should the risk be handled by the risk manager?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Ignore the risk and concentrate only on the pertinent risks.
- B. Remove the risk from the risk register and inform the project manager that it is no longer valid.
- C. Close the risk during the next risk board meeting and keep it in the risk register. — đáp án hiện tại
- D. Conduct a risk analysis to determine how an inappropriate risk was formally accepted.