Câu 166: PMI Risk Management Professional

An external vendor needs to be contracted to provide additional capacity and expertise to a project team to reduce the probability of delays in a project. The contracts department is raising a concern about confidentiality risks not addressed in the proposed contract and missing from the risk register. What should the…

Nội dung câu hỏi

An external vendor needs to be contracted to provide additional capacity and expertise to a project team to reduce the probability of delays in a project. The contracts department is raising a concern about confidentiality risks not addressed in the proposed contract and missing from the risk register. What should the risk manager do next?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Communicate the identified residual risk. — đáp án hiện tại
  2. B. Implement the risk response plan.
  3. C. Assess the identified secondary risk.
  4. D. Implement the risk contingency plan.