Câu 164: PMI Risk Management Professional
A project manager and risk manager are working on a new hotel development project for their organization and have completed the risk analysis processes for the identified risks. They determined that the organization might not be able to handle the consequences of some of the high-priority risk items, and the project's…
Nội dung câu hỏi
A project manager and risk manager are working on a new hotel development project for their organization and have completed the risk analysis processes for the identified risks. They determined that the organization might not be able to handle the consequences of some of the high-priority risk items, and the project's objectives and designs cannot change. The team is preparing risk responses for these high-priority risks. Which risk response strategy will effectively manage these high-priority risks?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Risk mitigation
- B. Risk avoidance
- C. Risk escalation — đáp án hiện tại
- D. Risk transference
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.