Câu 128: PMI Risk Management Professional
In the country where a project is being executed, customs procedures are complex and change frequently. During the risk identification process, the project team identifies a risk related to delays in customs on substantial equipment that will likely occur. Equipment delays on this project could lead to project cancell…
Nội dung câu hỏi
In the country where a project is being executed, customs procedures are complex and change frequently. During the risk identification process, the project team identifies a risk related to delays in customs on substantial equipment that will likely occur. Equipment delays on this project could lead to project cancellation. Why should a mitigation plan be developed for this risk?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. This is a financial risk.
- B. This task is on the critical path.
- C. A response plan should be developed for all risks.
- D. This is a high-priority risk. — đáp án hiện tại