Câu 83: PMI Risk Management Professional

A project manager has a two-month project with three project team members. The project sponsor does not agree with the project manager that a risk planning process is necessary, since the project is very small. Would it be appropriate for the project manager to implement some level of risk management?

Nội dung câu hỏi

A project manager has a two-month project with three project team members. The project sponsor does not agree with the project manager that a risk planning process is necessary, since the project is very small. Would it be appropriate for the project manager to implement some level of risk management?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Yes, even small projects may require risk planning. — đáp án hiện tại
  2. B. No, small projects do not usually require risk planning.
  3. C. No, risk planning should be initiated with the sponsor's consent.
  4. D. Yes, the risk planning process implementation is ultimately the project manager's decision.