Câu 49: PMI Risk Management Professional

A certain risk is identified for a major project, and the risk response is planned. However, the analysis reveals a high probability for a secondary risk which will be tolerated based on the organization’s risk thresholds. The secondary risk is subsequently registered. During project execution, the primary risk occurs…

Nội dung câu hỏi

A certain risk is identified for a major project, and the risk response is planned. However, the analysis reveals a high probability for a secondary risk which will be tolerated based on the organization’s risk thresholds. The secondary risk is subsequently registered. During project execution, the primary risk occurs, the planned action is taken, and the secondary risk emerges. What two actions should the risk owner take? (Choose two.)

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Update and communicate assessments of the secondary risk’s impact. — đáp án hiện tại
  2. B. Implement the secondary risk response and update the project documents. — đáp án hiện tại
  3. C. Set the corresponding trigger conditions to the secondary risk.
  4. D. Engage the project manager to authorize the secondary risk’s response.
  5. E. Conduct meeting with all stakeholder to agree on post impact solutions.