Câu 97: PMI Risk Management Professional
A project manager is running a high-cost telecommunications project. There is a monthly status meeting, and the risk manager should provide an update to the project team and project sponsors on major risks. What risk related information should be included in the monthly status meeting of this complex project?
Nội dung câu hỏi
A project manager is running a high-cost telecommunications project. There is a monthly status meeting, and the risk manager should provide an update to the project team and project sponsors on major risks. What risk related information should be included in the monthly status meeting of this complex project?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Top priority risks at present, risks closed in the last period, milestone changes
- B. Top priority risks at present, risks that have occurred, risk management plan
- C. Top priority risks at present, risks that have occurred, changes in scope
- D. Top priority risks at present, risks that have occurred, risks closed in the last period — đáp án hiện tại