Câu 144: PMI Risk Management Professional

The company is a risk seeking organization, and has experienced measurable success based on their current strategy for growth. A new project has that exceeds the risk levels documented in the risk management plan. What would be the best course of action for the company to take with the project based on its current sco…

Nội dung câu hỏi

The company is a risk seeking organization, and has experienced measurable success based on their current strategy for growth. A new project has that exceeds the risk levels documented in the risk management plan. What would be the best course of action for the company to take with the project based on its current scope?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Monitor ongoing risks closely for any major changes.
  2. B. Perform a Monte Carlo simulation to understand possible risk outcomes.
  3. C. Cancel the project, as the overall level of risk remains unacceptable. — đáp án hiện tại
  4. D. Conduct a stakeholder meeting to validate stakeholder risk appetite.