Câu 156: PMI Risk Management Professional

During project execution, a project manager invites the stakeholders to a risk review meeting. During this meeting, a vendor highlights that the mitigation plan for a schedule risk has generated an additional risk. What should the risk manager do first?

Nội dung câu hỏi

During project execution, a project manager invites the stakeholders to a risk review meeting. During this meeting, a vendor highlights that the mitigation plan for a schedule risk has generated an additional risk. What should the risk manager do first?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Update the new risk in the risk register.
  2. B. Plan responses for the new risk. — đáp án hiện tại
  3. C. Passively accept the new risk.
  4. D. Add the new risk to the watch list.